Controlled explosion of the cooling towers 1 to 4 in Thierbach power station
Explosion of the four towers in one event
Client:
Biq GmbH
Project management TVF:
Region South/East
Time frame:
Begin: January 2006 End: August 2006
Job description:
- Controlled explosion of the four cooling towers with a one second time lapse between each explosion
- Preparation of the rubble with a heavy plant crusher and subsequent recycling
- Clearance of the site
Special factors:
- Completion of an evidence securing operation in a nearby catering building for the settlement of any eventual damage caused
- Closing of the main road B48 by the police to create a safety zone
Quantity details:
- Height of the cooling towers 90 metres
- Diameter at the top 36.90 metres
- Diameter at the base 32.80 metres
- Total material 21,000 tons
Controlled explosion details:
- Drilled holes and number of detonators 1,932
- Fuse cable Dynacord 1,800 metres
- Explosive Eurodyn 2000 175 kilograms
- Creation of fall slots (pre determined breaking points) with a cable excavator
- Attachment of circa 10,000 square metres of fleece matting and circa 3,000 square metres of wire netting to prevent flying grit