Decommissioning of the power plant boiler house in Lippendorf
Client:
Biq GmbH
Address: Sigmund-Bergmann-Strasse 1, 03222 Luebbenau
Project management TVF:
Region South East, Luebbenau
Time frame:
Begin: February 2005; End: June 2006
Job description:
- Complete sanitation of pollutants in only 14 weeks with approx 95 workers
- Preparation of a controlled explosion including static safety measures
- Partial deconstruction (circa 2,000 tons) of boiler house number 1, due to its proximity to the coal-feed of the new power station
- Controlled explosion of the 7 boilers and subsequent sorting of the scrap steel into containers
- Complete removal of underground rubble with subsequent preparation, recycling and refilling of the site
Quantity details:
- diverse leak proofing materials on portholes and flanges etc.
- Mineral wool insulation on the boiler walls 38,000 square metres
- Asbestos façade 7,400 square metres
- Redeveloped area circa 400,000 cubic metres
- Scrap steel circa 24,000 tons
- Concrete rubble circa 19,000 cubic metres
- Excavation volume with refilling 25,000 cubic metres
Controlled explosion details:
- Hollow space explosion of the water-filled supports
- Detonator cable Dynacord 1,200 metres
- Explosive Eurodyn 2000 120 kilograms
- 60 fuses