Deconstruction of cooling tower 2 in Lippendorf power station
Client:
Biq GmbH, Sigmund-Bergmann-Strasse 1, 03222 Luebbenau
Project management TVF:
Region South/East
Time frame:
Begin: April 2005; End: December 2005
Job description:
- Due to the proximity of the nearest homes (45 metres) it was decided that a controlled explosion was not possible
- A tower gantry was mounted in the centre of the cooling tower
- A tunnel for machinery and communication technology was created as protection against falling concrete
- Demolition of the cooling tower wall using hanging hydraulic shears down to 54 metres
- Integration of the hydraulic equipment as a counterweight for the crane
- Disassembly of the tower gantry
- Demolition down to ground level
- Preparation and recycling of the rubble in grit size 0-63 millimetres and backfilling of the site
Quantity details:
- Height of the cooling tower 113 metres
- Diameter at the top 48.20 metres
- Diameter at the base 80.00 metres
- Material circa 6,000 cubic metres