Deconstruction of cooling tower 2 in Lippendorf power station

Client: 

Lippendorf/ Deconstruction of cooling tower 2

Lippendorf/ Deconstruction of cooling tower 2

Biq GmbH, Sigmund-Bergmann-Strasse 1, 03222 Luebbenau

Project management TVF:

Region South/East

Time frame:

Begin: April 2005; End: December 2005

Job description:

  • Due to the proximity of the nearest homes (45 metres) it was decided that a controlled explosion was not possible 

    Lippendorf/ Deconstruction of cooling tower 2

    Lippendorf/ Deconstruction of cooling tower 2

     

  • A tower gantry was mounted in the centre of the cooling tower
  • A tunnel for machinery and communication technology was created as protection against falling concrete
  • Demolition of the cooling tower wall using hanging hydraulic shears down to 54 metres
  • Integration of the hydraulic equipment as a counterweight for the crane
  • Disassembly of the tower gantry
  • Demolition down to ground level
  • Preparation and recycling of the rubble in grit size 0-63 millimetres and backfilling of the site

Quantity details:

  • Height of the cooling tower 113 metres
  • Diameter at the top 48.20 metres
  • Diameter at the base 80.00 metres
  • Material circa 6,000 cubic metres

 