Partial deconstruction of the combined heat and power plant (CHP) Altchemnitz
Partial deconstruction of decommissioned facilities and equipment, including waste oil depot, pump-house, waste oil basins, skimming pool, two tanks with a capacity of 3,200 cubic metres each.
Client:
Stadtwerke Chemnitz AG, Augsburger Strasse 1, 09111 Chemnitz
Project management TVF:
Region South/East
Time frame:
Begin: August 2003; End: November 2003
Job description:
All work in accordance with TRGS 519, working in contaminated areas, dismantling of steel constructions with a crane, all tasks performed with the plant fully operational and under limiting conditions with regard to fire safety.
Quantity details:
- Manual steel deconstruction 220 tons
- Clearing of contaminated materials, man-made fibres
- Manual demolition 1,000 cubic metres